RB Spectra is specialised in Engineering, Design, Installation, Commissioning and maintenance of Electrical Power and Instrument System
Covering most area of Offshore platforms, onshore plants (Oil & Gas, Power plant Industries), etc. Starting this business services on 2001, we have complete facilities and resources to support the full solutions to your electrical and instrumentation problems.
RB Spectra also specialised in cable specification and coding to suite your application purpose.
Our Electrical Services
- High/Medium/Low Voltage Power System
- Cabling Work
( Laying, glanding ,termination and Testing) - Panel for Switch gear, Transformer, Main Switch Board ,Distribution Board, , etc services
- Indoor and Outdoor Lighting and fittings included ZONE 1 and 2.
- UPS System
- Eexe,Eexd and Wheather proof Junction Box.
- Fabrication Work for Support/Bracket for Electrical Equipment.
- Busduct Cast Resin Type.
- Retrofit work for Switch Gear and MCC panel.
Our Instrument Services
- Field instrumentation installation and calibration
(All Type of field Devices ) - Panel and Junction Box installation, wiring and fabrication
- Turbine control panel upgrade
- Cabling Work
( Laying,glanding,termination and testing ) - Fabrication Work for Support/Bracket for instrument Equipment.
- Tubing and fittings design and installation.
Project Information
Customer information | Work Description | Completion Date |
---|---|---|
Petronas Gas Berhad | Provision of Engineering, Procurement, Installation, Testing & Commissioning Work of New Surge Protection Device (SPD) System at GPP B Tok Arun, Paka. | Oct. 2005 – March 2006 |
Petronas Carigali Sdn. Bhd. – Kertih | Vibration Monitoring Upgrade at Tiong A Gas Compressor Train-A. Offshore Platforms | Feb. – April 2002 |
Petronas Carigali Sdn. Bhd. – Miri | Supply, install, Test and Commission of Baronia Turbo Compressor Online Monitoring System – Baronia offshore Platform – off Sarawak Coast | May – August 2002 |
Petronas Carigali Sdn. Bhd. Kertih | Supply, install, Test and Commission of On-line Vibration Monitoring at Pulai A Platform. offshore Platform | May – August 2002 |
Exxonmobil Exploration & Prodtn Mlysia Inc. | Provision and Installation of One (1) Unit On-line Condition Monitoring System for Semangkok-A FSE244. | Oct. 2002 – Jan. 2003 |
Exxonmobil Exploration and Production Malaysia Inc. | Provision of Bently Nevada’s Service Representative for Vibration Monitoring Work – FSE278. | Oct. 2002 – Jan. 2003 |
Petronas Gas Berhad GPP-B | The Provision to Construct, install and Commission On-line Analyzing Monitoring System for Amine Pump at GPP Complex B(GPP-B) Paka, Dungun, Terengganu. | Oct. 2002 – Feb. 2003 |
Petronas Carigali Sdn Bhd-Sarawak Operation | Provision of Technical Support Services I.e One (1) Technician and One (1) Machine Diagnostic Specialist (MDS) for Bayan GT703 Bently Nevada Vibration Monitoring System, PCSB-Sarawak Operation. | Oct. 2002 – Jan. 2003 |
Petronas Carigali Sdn Bhd | Provision for the Upgrading of Bently of Nevada 7200 Series Vibration Monitoring System at Tiong-A Platform P3/SO/F036 | Dec.2003 |
Talisman (M) Ltd. | Provision of Vibration Analysis On Export Compressor for BR-A CPP Project. | Dec.2003 |
Petronas Carigali Sdn Bhd – SKO | Provision of Bayan A GT-703 Gaslift/Export Compressor Vibration System Retrofit | Dec. 2003 |
Bumiwangsa | PM 9 Fire & Gas Upgrading Contract to Supply Cable, Installation Materials and Labour for Erection Works at Tiong-A. | Jan. 2004 |
Bumiwangsa | PM 9 Fire & Gas Upgrading Contract to Supply Cable, Installation Materials and Labour for Erection Works at Tinggi-A. | Jan. 2004 |
Petronas Carigali Sdn Bhd – Kerteh Operations | Provision to Upgrading of Vibration Monitoring System for Supply of Hardware, Software & Consumables Installation and Commissioning at Tinggi A. | April 2004 – June 2005 |
Petronas Carigali Sdn Bhd – Sabah Operations | Provision to Upgrade the Existing Monitoring System for Turbo Compressors, K-6360, K-6310 and K-6260 at ERB West A Platform. | April 2004 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply Control Valve & ITS Associated Accessories for Dulang C Platform. | May 2004 – Oct. 2007 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply Control Valve & ITS Associated Accessories for Dulang A Platform. | July 2004 – Dec. 2004 |
Exxonmobil Exploration and Production Malaysia Inc. | Provision to Upgrading of Vibration Monitoring Equipment/accessories for Semangkok A. | June – Aug. 2004 |
Petronas Gas Berhad | Price Agreement for the Rental of Skid Tank Mono Ethylene Glycol (MEG) at GPP1. | June 2004 |
Abb | PM 9 Fire & Gas Upgrading Contract to Supply Cable, Installation Materials and Labour for Erection Works at Bekok A, B and C. | June 2004 |
Petronas Carigali Sdn Bhd – Kerteh | Provision to Upgrading of Vibration Monitoring System for Turbo Generators at Dulang and FSO | July 2004 |
Petronas Carigali Sdn Bhd – SKO | Provision to Upgrade BNGB-WIM P8200/10 Vibration System for Petronas Carigali Sdn Bhd Sarawak Operations (PCSB-SKO) | Aug. 2004 – Oct. 2005 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply Control Valve & ITS Associated Accessories for Dulang D Platform. | Sept. 2004 – March 2005 |
Petronas Gas Berhad | Price Agreement for the Rental of Gas Detector (Portable, Personal & Intelligent) for Turnaround at POD, PGB. | Sept. 2004 – Nov.2004 |
Petronas Gas Berhad | Intelligent 4-in-1 Gas Detector – Stand Alone | Oct. 2004 |
Petronas Carigali Sdn Bhd – SBO & SKO | Provision of Vendor Support Services for Vibration Monitoring System of Rotating Equipment for Petronas Carigali Sdn Bhd – Sabah Operations (PCSB-SBO) and Petronas Carigali Sdn Bhd – Sarawak Operations (PCSB-SKO)-service Agreement | Dec. 2004 – Dec. 2007 |
Petronas Carigali Sdn Bhd – PMO | Provision of Upgrading Five Units of Motor Operated Valve at Bekok C Paltform. | Dec. 2004 – May 2005 |
Petronas Carigali Sdn Bhd – SKO | Provision for the Upgrading of G5600/5610/5620 Alstom Turbo Generators Vibration Monitoring System at BNG-B Platform | Feb. 2005 – Feb. 2006 |
Petronas Carigali Sdn Bhd – SKO | Provision for On-line Monitoring System for Two (2) Units Water Injection Pump at BNG-B for Petronas Carigali Sdn Bhd – SKO | Feb. 2005 – Oct. 2005 |
Emerson Process Management | Provision for the Machinery/asset Condition Management System for Three (3) Turbine Generators and One (1) Turbine Gas Compressor at Baram South Platform | Feb. 2005 |
Petronas Carigali Sdn Bhd – Sabah Operations | Provision to Upgrade the Vibration Monitoring System for Three (3) Units of Solar Gas Turbine at ERB West Platform, PCSB-SBO. | April – August 2005 |
Delcom Services Sdn Bhd / Petronas Carigali Sdn Bhd Kerteh | Provision of Upgrade the Vibration Monitoring System for 2 Units of Turbo Compressor – Bekok C Compressor | April 2005 – May 2005 |
Petronas Carigali Sdn Bhd – Sabah Operation | Provision of Online Monitoring System for Samarang Gas Turbine Compressor. | July 2005 |
Talisman (M) Ltd | Monthly VMS (Bop Machine) for Block PM-305 South Angsi Field. – (Talisman-SAA) | Oct. 2005 |
Talisman (M) Ltd | Provision for Monthly VMS (Bop Machine) for Block PM-305 South Angsi Field. (Talisman-SAA) | March 2006 |
Exxonmobil Exploration and Production Malaysia Inc. | Provision for Supply of Bently Nevada Parts for Emepmi’s Operations – Price Agreement | March 2006 |
Tanjung offshore Services Sdn Bhd / Petronas Carigali Sdn Bhd PMO | Provision of Upgrading Fire and Gas System at Tukau Platform. | Sept. 2006 |
Petronas Carigali Sdn Bhd – PMO | Provision of Technical Support Condition Based Monitoring (CBM) Services for PCSB-PMO. | Nov. 2006 – Nov. 2009 |
Petrofac (M-pm304) Ltd. | Provision of Vibration Survey for MOPU Rotating Equipment. | Nov. 2006 |
Tanjung offshore Services Sdn Bhd / Petronas Carigali Sdn Bhd-SBO | Provision of Supply Manpower for the Installation of Siemens Control Panel Retrofit at Samarang Platform. | April 2007 |
Exact Control Sdn Bhd / Petronas Carigali Sdn Bhd-PMO | Provision of Supply, Installation & Commissioning of Fusible Plug Loop System at Bekok-a Platform. | March 2007 – April 2007 |
Tanjung offshore Services Sdn Bhd / Petronas Carigali Sdn Bhd PMO | Provision of Upgrading Fire and Gas System at Kepong-A and Tiong-B Platform. | March 2007 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply, Testing and Commissioning for Bently Nevada Equipment. | March 2007 – April 2007 |
Ge Power Systems/ | Provision of Conceptual Machine Monitoring System at Polyethylene . | March 2007 – July 2007 |
Centralise Utility Facilities | Provision of instrument Cable Modification for TNB Hardwired at CUFK and CUFG. | May 2007 – July 2007 |
Ge Power System/ TNB Kenyir | Provision of Installation Vibration Monitoring System at TNB Hydro Kenyir Project. | July 2007 – August 2007 |
Tanjung offshore Services Sdn Bhd / Petronas Carigali Sdn Bhd PMO | Provision of Installation Fire & Gas System at Tukau Platform – Variation Order. | July 2007 |
Talisman (M) Ltd | Provision of Vibration Monitoring for Block Pm-3 CAA and PM-305 – SAA, Bunga Raya A/D/E and Bunga Orkid A. | July 2007 |
Sapuracrest Power Services / Petronas Carigali Sdn Bhd-PMO | Provision of Installation Air Raft for Rolls Royce Allison Pilotless Dual Fuel Nozzle Upgrade at Angsi Platform. | Sept. 2007 |
Petronas Carigali Sdn Bhd – PMO | Provision of Installation and Upgrading of Citrix Server Application for Tiong-A Bently System 1 Onshore Remote Display. | Jan. 2008 – March 2008 |
Tanjung offshore Services Sdn Bhd / Petronas Carigali Sdn Bhd SBO | Provision of Fire and Gas Detection System for City Gate Metering Station at Petronas Carigali – SBO. | May 2008 – Sept. 2008 |
Mre Power Technologies/ge Power System | Provision of Installation of Vibration Monitoring System at TNB Kenyir for Unit Train 1,2,3 & 4. | May 2008 – July 2008 |
Petronas Carigali Sdn Bhd – PMO | Provision to Upgrade Bently Nevada Vibration Monitoring System for Dulang. | May 2008 – Dec. 2008 |
Talisman (M) Ltd | Provision of SAA Gas Lift Compressor & Water injection Pump Structural Vibration Analysis | July 2008 – Dec. 2009 |
Trisystems Sdn Bhd / Petronas Carigali – PMO | Provision of Supply Manpower for Installation at Dulang-A, Dulang-B and Dulang-C. | August 2008 |
Petronas Carigali Sdn Bhd- PMO | Provision to Upgrade Bently Nevada at Tiong. (Cable Replacement for Compressor VMS) | August 2008 |
Petronas Carigali Sdn Bhd-PMO | To Perform Lube Oil Analysis for Tm Provision for Lubricating Oil Analysis for All Turbo Machinery Units for PCSB-PMO. | Sept. 2008 – Sept. 2011 |
Petronas Carigali Sdn Bhd-PMO | Provision to Upgrade Bently Nevada at Tiong. (Cable Replacement for Generator VMS) | Feb.2009 |
Petronas Carigali Sdn Bhd-SKO | Provision of Health Check Audit of Bently Nevada 3500 Series/system 1 at Baronia, Bayan, D35 and Baram Platform for PCSB-SKO. | Feb. 2009 – Feb 2010 |
Petronas Carigali Sdn Bhd-SBO | Provision of Health Check Audit of Bently Nevada 3500 Series/system 1 at Samarang and ERB West Platform for PCSB-SBO. | August 2008 – August 2009 |
Petronas Carigali Sdn Bhd-PMO | Provision of Bently Nevada Vibration Monitoring System Maintenance Services for PCSB-PMO. | July 2007 – July 2009 |
Talisman (M) Ltd | Provision of SAA Gas Lift Compressor Parallel Operation and Vibration and Evaluation | March 2009 |
Tanjung New Energy Service/petronas Carigali Sdn Bhd-SKO | Provision of Supply, Installation and Commissioning for Reciprocating Online Monitoring System for PCSB-SKO. | April 2009 |
Tanjung Csi/petronas Carigali Sdn Bhd-SKO | Installation of Fire & Gas for COTP at PCSB-SKO. | July 2009 |
Emerson/petronas Carigali Sdn Bhd-SBO | Machine Condition Monitoring System (MCMS) for Kinabalu Project. | July 2009 |
Petronas Carigali Sdn Bhd-PMO | Provision of Bently Nevada Vibration Monitoring System Upgrading for TCOT Vapour Recovery Compressors C-270A, C-270B, C-270C and C-270D for PCSB-PMO. | Nov. 2009 – May 2011 |
Tanjung Csi/petronas Carigali Sdn Bhd-PMO | Provision of Installation of Gas Compressor Fire Gas System at Tiong-A. | Jan. 2010 |
PTT Aromatics & Refining Public Company Limited | Provision of Fire Heaters Emergency Shutdown (ESD) Software Reengineering at PTT Aromatics & Refining Public Company Limited. | March 2010 |
Sarawak Shell Berhad | Provision of Condition and Performance Based Maintenance System for B11K-A, F23VLAP and St.Joseph Redevelopment for SSB/SSPC. | May 2010 – May 2013 |
Exxonmobil Exploration and Production Malaysia Inc / Perunding Ranhill Worley Sdn Bhd | Provision of Lawit-A Compressor Restage Projects/Vibration Study | April 2010 – May 2010 |
Exxonmobil Exploration and Production Malaysia Inc | Provision of Bently Nevada Vibration Monitoring System & Technical Support | June 2010 |
Delcom Services Sdn Bhd/GPPa | Provision of TT4 UCP Upgrade Project at KCS-A | May 2010 |
Delcom Services Sdn Bhd/petronas Carigali Sdn Bhd-PMO | Provision of Installation at Dulang-B Tcp Upgrade – Construction Works for 3 Units of Solar Gas Compressors. | Nov. 2010 |
Newfield Peninsular Malaysia | Provision of Dynamic Design Verification for Two(2) Units of Gas Compressor Module at Newfield’s East Belumut-A Platform. | August 2010 |
Petronas Carigali Sdn Bhd-PMO | Provision to Upgrade Bn System 1 for Dulang-B Compressor and Water injection Pump for Petronas Carigali-PMO | Oct. 2010 |
Emerson Process Management | The Supply & Installation of Machine Condition & Performance Monitoring System (CPBM) for KPOC Platform. | Feb. 2011 |
Turboservices Sdn Bhd | Provision of Installation Tiong-A Tcp Upgrade – Construction Works for 2 Units of Solar Gas Compressor. | May 2011 – Oct. 2011 |
Exxonmobil Exploration and Production Malaysia Inc | Provision for Bently Nevada Vibration Monitoring System Upgrade, Technical Support and Spare Parts | June 2011 |
Petronas Dagangan Berhad | Provision the Price Agreement of Vibration Analysis for Pump and Motor at Kerteh Fuel Terminal, Kerteh Aviation Fuel Terminal and Kuantan Fuel Terminal. | May 2011 |
Samsung Eng. Co.ltd. | Provision of Supply & Installation of Condition Base Monitoring System (CBMS) for PCSB-SBO & Gas Terminal Project. | June 2011 |
Turboservices Sdn Bhd | Provision of Turbo Tronic 4 Upgrade Control at GPP3 | Sept. 2011 |
Trisystem Eng.sdn Bhd | Provision of Relocating Gas Detector at D35 for PCSB-SKO | Sept. 2011 |
Petronas Carigali Sdn Bhd-PMO | Provision of Supply, Installation & Commissioning of Fusible Plug Loop System at Duyong, Dulang, Tinggi and Pulai Platforms and Onshore Gas Terminal(OGT) for PCSB-PMO. | Oct. 2011 |
Berkat Honeywell/ | Supply of Field instrument and Installation Work for Turbo Expander Control System R/RT – 401 at GPP3 Gas Processing Plat Complex–A GPP-A, Paka , Trg | April 2012 |
Deleum Services/petronas Gas Berhad | The Engineering, Construction and Installation for Retrofitting Works for Turbotronic 4 Upgrading Project at GPP-2, GPP-A, Kerteh Terengganu. | July 2012 |
Petronas Carigali Sdn Bhd-PMO | Provision to Upgrade Vibration Monitoring System Bn System 1 for Gas Compressor at Dulang B Platform. | August 2012 |
Talisman | Provision of Bently Nevada Condition Based Monitoring Services | Oct. 2012 |
Deleum Services | The Engineering, Construction and Installation for TCOT Control Retrofit Project. | Nov. 2012 |
Petronas Carigali Sdn Bhd-SBO | Provision of Vendor Support Services for Vibration Monitoring System of Rotating Equipment for PCSB-SBO | Jan. 2013 |
Petronas Dagangan Berhad | PA for Vibration Monitoring & Pump Alignment for Pump and Motor at PDB Eastern Terminals Consist of Kerteh Fuel Terminal, Kerteh LPG, Kerteh Aviation Fuel Terminal and Kuantan Fuel Terminal. | May 2013 |
Petronas Carigali Sdn Bhd-PMO | Provision to Supply and Deliver Fusible Plug Loop Panel & Tubing for Rejuvenation Project at Terengganu Crude Oil Terminal (TCOT) and Onshore Slug Catcher (OSC) for PCSB-PMO. | June 2013 |
Sarawak Shell Berhad | Provision of Condition and Performance Based Maintenance System for Gumusut-KAKAP Field | Dec. 2013 |
Pc Methanol | Provision for Condition Based Monitoring (CBM) Services for PC Methanol Sdn Bhd | March 2014 |
Petronas Gas Berhad | Turbomachinery Instrumentation K-501 | July 2014 |
Sarawak Shell Berhad | CPBM TSS – PLA & RCA | August 2014 |
Petronas Carigali Sdn Bhd-PMO | Provision of Bently Nevada Condition-based Monitoring Services, Machine Diagnostics and Supply of Spares (Contract) – PMO | August 2015 – August 2017 |
Sarawak Shell Berhad | Provision of Bently Nevada Condition-based Monitoring Services, Machine Diagnostics and Supply of Spares – Sarawak Shell | August 2015 – August 2017 |
Talisman | Provision of Bently Nevada Condition-based Monitorng Services, Machine Diagnostics and Supply of Spares(Contract) – Talisman | August 2015 – August 2017 |
PDB | Price Agreement of Vibration Monitoring and Analysis at PDB Eastern Region Terminals | Sept. 2015 – Sept. 2017 |
Petronas Carigali Sdn Bhd-PMO | Tiong A GTGS BN3500 Installation | Sept. 2016 |
Petronas Carigali Sdn Bhd-PMO | System 1 Software for Duyong | Oct. 2016 |
Sarawak Shell Berhad | Provision of Condition and Performance Based Monitoring (CPBM) Technical Support Services in SSB/SSPC | Feb.2017 – Feb.2020 |
Ge Power | 8 Unit Sales Gas Vibration Sensor Installation at GPS | Nov. 2016 |
Talisman | KNB-BN3500 Upgrade for COTP P-1310 & P-1320 | April 2016 |
Petronas Carigali Sdn Bhd-PMO | Provision to Supply, Install and Commission 3 Units Bn3500 VMS for 3 Units Gas Turbine Generator at Bekok A Platform. | Sept. 2015 |
Petronas Carigali Sdn Bhd-PMO | BN Smartsignal Project at PMO Paltform | May 2016 |
Petronas Carigali Sdn Bhd-PMO | System 1 Evolution Installation for 9 Unit BN3500 Angsi Platform | March 2017 |
Petronas Gas Berhad | Engineering, Procurement, Installation & Commissioning of Bently Nevada 3500 Rack & System 1 Upgrading Project at Utilities Kertih(UK) and Utilities Gebeng(UG), Petronas Gas Berhad. | Feb. 2017 – July 2019 |
Sarawak Shell Berhad | Provision of Bently Nevada Condition-based Monitoring Services, Machine Diagnostics and Supply of Spares – SSB | Sept. 2017 – Sept. 2019 |
Uzma | Technical Supply Agreement | Sept. 2017 |
Repsol | Provision of Bently Nevada Condition-based Monitorng Services, Machine Diagnostics and Supply of Spares(Contract) | July 2017 – July 2019 |
Petronas Carigali Sdn Bhd-PMO | Provision of Bently Nevada Condition Based Monitoring Services, Machine Diagnostics and Supply of Spares | August 2017 – August 2019 |
Petronas Carigali Sdn Bhd-PMO | General Electrical for Dulang B | Feb. 2018 |
Kebabangan Petroleum Operating Company | Provision for Supply, Configuration, Licensing and Maintenance Support of Meridium System | April 2018 – April 2021 |
Petronas Carigali Sdn Bhd-PMO | To Purchase & install System 1 for GCM | Sept. 2018 |
Petronas Carigali Sdn Bhd-PMO | Duyung Tg System 1 Enablement | Sept. 2018 |
Lotte Chemical Titan (M) Sdn Bhd | Au Provision of EPC for Vibration Monitor | Oct. 2018 |
Petronas Carigali Sdn Bhd-PMO | Ge Smart Signal | Oct. 2018 |
Petronas Gas Berhad | Provision of Bently Nevada 3500 Upgrade for PGB GPU GP Santong (GPS) | Dec. 2018 |
PPTSB | Provision of BN3500 GEN1 Upgrade for PPTSB Aromatics | Dec. 2018 |
Ge Power | 3701 Installation at CUF – Supply Manpower, Consumables | Jan. 2019 |
Petronas Carigali Sdn Bhd-SBO | System 1 Supporting Service Agreement | April 2019 |
Petronas Carigali Sdn Bhd-PMO | TIA System 1 Upgrade – Phase 2 | April 2019 |
Petronas Carigali Sdn Bhd-PMO | Provision for Installation of Ranger Pro | May 2019 |
Petronas Carigali Sdn Bhd-PMO | To Purchase 3 Units Monitoring Device Anomalert for SWLP together With Installation | May 2019 |
Petronas Carigali Sdn Bhd-SBO | Anomalert Installation at KNNG Platform | August 2019 |
Petronas Nasional Berhad – MLNG & PFLNG | Price Agreement for Supply and Delivery for Bently Nevada Parts to Malaysia LNG Sdn Bhd & Petronas Floating LNG 1 (L) Ltd. – 3 Years Contract (19/08/2019 – 18/08/2022) | 19/08/2019 – 18/08/2022 |
Petronas Carigali Sdn Bhd-PMO | Provision of Bently Nevada Condition Based Monitoring Services, Machine Diagnostcs and Supply of Spares (20/8/2019 – 19/8/2020) | 20/08/2019 – 19/08/2022 |
Petronas Gas Berhad | Provision of Engineering, Procurement, Installation and Commissioning of Bently Nevada System 1 Upgrade and Remote Monitoring Center at Gas Processing & Utilities, Petronas Gas Berhad. | Oct. 2019 |
Sea Hibiscus | Provision of Bently Nevada Equipment Support Services for Sea Hibiscus Sdn Bhd. | Dec. 2019 |
Sarawak Shell Berhad | Provision of Condition and Performance Based Monitoring (CPBM) Technical Support Service in SSB/SSPC – Period 10 Feb.2020 to 9 Feb. 2021 | Jan. 2020 |
Customer Information | Work Description | Completion Date |
---|---|---|
Petronas Carigali Sdn Bhd – PMO | Provision of Upgrading Project for Fire and Gas at PM9 at Bekok A, B & C Platform. | Oct. 2004 |
Petronas Carigali Sdn Bhd – PMO / Bumiwangsa | Provision of Upgrading of Fire & Gas at Pm-9 Platforms – Tiong A and Tinggi A Platforms | Oct. 2004 – Dec. 2005 |
PTB Resort Sdn Bhd | Pengubahsuaian dan Menaiktaraf Kerja-kerja Mekanikal dan Elektrikal yang Merangkumi Peralatan High Tension Peralatan High Tension, Capacitor Bank, Amf Board dan Kerja-kerja Berkaitan Di Primula Beach Resort Kuala Terengganu. | Aug. 2006 – Dec. 2006 |
Petronas Dagangan Berhad / MRE | Provision of Supply, Installation, Testing and Commissioning of Standby Generator Set and Capacitor Bank for Petronas Dagangan Berhad. | March 2007 – April 2007 |
Petronas Carigali Sdn Bhd-PMO / MRE | Provision of Electrical and Fire Fighting Systems Maintenance Services at Petronas Operation Complex (KOP) for Petronas Carigali Sdn Bhd-PMO. | March 2007 – Feb. 2009 |
Petronas Gas Berhad | Provision of Replacement 11KV High Fusing Unit & Oil Link Unit With Vacuum Circuit Breakers and Accessories at The Bomba Sub Station, GPPA, Kerteh, Terengganu. | Dec. 2007 |
Tanjung CSI Sdn Bhd | Provision of Upgrading Fire Notification System at BPCM, Gebeng. | March 2008 – July 2008 |
Kilang Sawit Panji Alam Sdn Bhd | Membekal Tenaga Kerja, Peralatan, Jentera dan yang Berkaitan Dengannya Bagi Memasang 2 Unit Meter Control Starter Panel. | July 2008 |
Petronas Penapisan (T) Sdn Bhd | Provision of Supply , Install, Commission Bus Coupler at Petronas Penapisan (T) Sdn Bhd. | Sept. 2008 |
Tanjung CSI Sdn Bhd | Provision of TMR Upgrading System Project at GPP 5 | Nov. 2008 |
Petronas Carigali Sdn Bhd – SBO | Provision of Upgrading of Circuit Breaker (ACB) for ERB West and Samarang Platforms for Petronas Carigali Sdn Bhd-Sabah Operation | March 2009 |
Petronas Gas Berhad | Provision of Electrical Cabling & Wiring Works (Emergency Lighting Replacement Project) at PGB. | July 2009 |
Tanjung CSI /MLNG | Provision of Supply & Install of FGS System Devices at MLNG1 | Jan. 2010 |
Petronas Carigali Sdn Bhd – SBO | Provision To Upgrade Motor Control Centre (MCC) 2 & 3 at Tembungo – A Platform for PCSB-SBO. | July 2010 |
Petronas Carigali Sdn Bhd-PMO / MRE | Provision of Electrical and Fire Fighting Systems Maintenance Services at Petronas Operation Complex (KOP) for Petronas Carigali Sdn Bhd-PMO. | Aug. 2010 – July 2013 |
Tanjung Newenergy / Petronas Carigali Sdn Bhd-PMO | Provision of Supply, Install, Testing & Commissioning of Undistruptable Power Supply(UPS). | Dec. 2010 |
MRE / Petronas Carigali Sdn Bhd-PMO | Provision To Supply, Deliver, Testing & Commission of Three(3) New Power Transformers for Duyong Platform for PCSB-PMO. | May 2010 |
Tanjung CSI / Petronas Carigali Sdn Bhd-PMO | Provision of Revamp Distributed Control System at TCOT & OSC. | Jan. 2011 |
Trisystem | Provision for SIS Upgrading at Bayan Platform | Feb. 2011 |
Ranhillworley Parson/ Exxonmobil | Provision of Guntong-d (GUD) Fuel Gas Superheater Upgrade Project | April 2011 |
Petronas Carigali Sdn Bhd – SBO | Provision To Retrofit Motor Control Centre (MCC) MCC-101 and MCC-102 at Samarang and ERB West Platform for PCSB-SBO. | Sept. 2011 |
Petrofac | Provision of Manpower and Equipment for Electrical Protection Relay Calibration During MOPU. | March 2011 |
Ranhillworley Parson/ Exxonmobil | Provision of Supply, Installation, Modification and Commissioning of Busduct System – Iba | June 2012 |
Ranhillworley Parson/ Exxonmobil | Provision of Retrofication and Modification of Lv Switchgear, MCC & Distribution Panels – Iba | June 2012 |
Ranhillworley Parson/ Exxonmobil | Provision of Modification of Switchgear and MCC Termination – Semangkoka | June 2012 |
MRE/shinryo | Provision of To Supply and Install Site office for GPPA & GPPb C/w Electrical and Mechanical Works. | July 2012 |
Ranhillworley Parson/ Exxonmobil | Provision of Supply and Deliver of Lv Cast Resin Busduct | July 2013 |
Shinryo (Malaysia) Sdn Bhd | Provision of PGB Cogen Plant, Kerteh & Paka, Terengganu. | July 2013 |
Deleum Services | Provision of Package System Upgrade for Pulai-a Centaur 40 Compressor Package. | Jan. 2013 |
MRE / Petronas Gas Berhad | Provision of Upgrading 415v Switchboard for Non-process Area at Petronas Gas Berhad, GPPA, Kerteh. Contract No.: Smso/c3/rfx 6200055300 (S130593) | Feb. 2014 |
Sedia Teguh Sdn Bhd | Provision of Turbine Control Panel Upgrade at Samarang Platform_rev02 | April 2014 |
Deleum Services | Provision of Processed Po-60000239-GPP4 Subcontracor Services T199 (Dssb-project) | May 2014 |
Deleum Services | Gatir Upgrading Works at Tiong-a 2 X C40psu | May 2014 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply and Delivery Work Studio for PCSB-PMO. | June 2014 |
Petronas Carigali Sdn Bhd – PMO | Provision of Angsi Cable Replacement | June 2014 |
Petronas Carigali Sdn Bhd – PMO | Provision for Engineering, Procurement, Construction, Installation and Commissioning (Epcic) for Protection Relay Upgrade at Pscb-PMO – Dulang & Duyong. | July 2014 |
Exact Automation Sdn Bhd | Onshore Slug Catcher for OSC | July 2014 |
Exact Automation Sdn Bhd | Provision of Proposal for Fire & Gas at Terengganu Crude Oil Terminal (TCOT) | Aug. 2014 |
Petronas Carigali Sdn Bhd – PMO | Provision of Supply and Delivery Work Studio for PCSB-PMO. | Nov. 2014 |
Petronas Gas – Gpu | Engineering, Procurement, Construction and Commissioning of Ngu2 Second Feeder Project at Utilities Plants Gebeng (Ug) Petronas Gas Berhad | Sept. 2014 |
INSTEP | The Provision of Electrical Services and Maintenance at INSTEP Campus. | April 2015 – 2018 |
Deleum | Provision of Subcon Work for Provision, Construction Services for Retrofitting Works for Turbotronic 4 Upgrading Project at Helang offshore Platform T208 JNOEX HIP CTRL & Package 2XC40GS | May 2015 |
Deleum | Provision of Subcontractor Services for Duyong System | July 2015 |
Petronas Gas Berhad-gebeng | Provision of Engineering, Procurement, Construction and Commissioning of HRSG Igniter System at Utilities Gebeng (UG) – PGB Gebeng | July 2015 |
Petronas Carigali Sdn Bhd-PMO | Provision for Supply, Installation and Commissioning of Air Circuit Breaker (ACB) for PCSB-PMO. | Sept. 2015 |
Petronas Gas Berhad | Provision of Procurement, Installation & Commissioning of 200KW MCC With External JB for Air Compressor (Portable Unit) at Gas Processing Plant Complex B | Oct. 2015 |
Petronas Carigali Sdn Bhd-PMO | Provision of General Electric Services for PCSB-PMO. 2 Years Contract | Feb. 2016 |
INSTEP | The Provision of Electrical Services and Maintenance at INSTEP Campus – Contract Period 5 May 2017 – 4 May 2018 | May 2017 – May 2018 |
KLCC | The Non Comprehensive of Electrical Maintenance Services for Rantau Housing, Petronas East Coast Regional office, Rantau Clinik and Petronas Properties (“The Works”) – 1 July 2017 – 30 June 2020 | July 2017 – June 2020 |
Petronas Carigali Sdn Bhd-PMO | Provision of General Electric Services for PCSB-PMO. 1 Year Contract | Feb. 2018 – Feb. 2019 |
Petronas Chemicals Ammonia Sdn Bhd | Provision of Electrical & Mechanical Maintenance of Building Insfrastructure | Feb. 2018 – Feb. 2020 |
KLCC Urusharta Sdn Bhd | Fencing Upgrading Works for Rantau Bukit & Rantau Laut Petronas, Rantau Housing Kertih. | July 2018 |
Petronas Carigali Sdn Bhd-PMO | Motor Control Center (MCC) Feeder Upgrade | Sept. 2018 |
Petronas Dagangan Berhad | The Price Agreement for The Periodical Electrical Installation Inspection, Explosion Proof Equipment and Fitting Inspection, Renewal of Generator Set Registration and Protection Relays Testing and Calibration for PDB Northen Region (ITQ No.: 6200247307) | April 2019 – April 2021 |
Petronas Chemicals Ammonia Sdn Bhd | Provision of Electrical & Mechanical Maintenance of Building Insfrastructure for Petronas Ammonia – Conract No: PK/PSS/SB1/N2018/6200209839 – LOE 15.2.2020 – 14.2.2021 | Feb. 2020 |